Project Timeline
NOTE: Click
on the number of the Action Step, below, to see a
description of what happened at that stage of the .........project.
Use your browser's BACK button to return to this
page.
Action Step
Start
Date
End
Date
Action
Taken (and Who's Got the Ball)
ISD
team meets with Clients / SMEs
3/9
3/9
ISD
team assesses project needs (task analysis)
3/9
3/19
ISD team prepares initial
proposal and statement of project goals
3/19
3/22
ISD
team identifies entry behaviors and characteristics
3/19
3/22
Clients / SMEs review initial proposal
3/26
3/26
ISD
team writes performance objectives
3/26
4/1
ISD
team develops criterion-referenced test items
3/26
4/1
ISD
team determines instructional strategy
3/26
4/1
9
Clients / SMEs review objectives,
test items, and instructional strategy
4/1
4/2
ISD team develops storyboard
draft of instructional materials
4/2
4/9
11
Clients / SMEs review storyboard draft
of instructional materials
4/9
4/9
ISD team meets with technical
support advisors/programming team
4/9
4/9
ISD
team develops pilot lesson materials
4/9
4/9
ISD team/Clients conduct
formative evaluation of pilot materials
4/9
4/16
15
ISD team revises instructional
materials as need after formative evaluation results
4/16
4/22
ISD
team designs complete instructional materials
4/23
4/30
ISD
team writes project abstract
4/23
4/30
Clients / tech team complete programming
and scripting of instructional prototype
4/23
4/30
Clients evaluate collaborative process
5/2
5/2
Clients implement training
5/2
6/17
Clients conduct summative evaluation
6/25
7/9